Concerns Raised Over Silchar Flyover Project Changes

A lawyer from Silchar has approached the Prime Minister’s Office to seek clarity on the proposed shortening of the Silchar flyover project. Advocate Dharmananda Deb raised concerns about the potential reduction of the originally planned 3.5-km flyover to two shorter segments. He is demanding transparency and accountability from the authorities regarding the project's approval process and land acquisition details. Deb's inquiries also include whether local residents had the opportunity to voice their opinions before any decisions were made. This situation highlights the importance of proper administrative procedures in significant infrastructure projects.
 | 
gyanhigyan

Silchar Lawyer Seeks Clarity on Flyover Modifications

A meeting was held on November 20 regarding the elevated corridor from Capital Point to Rangirkhari in Silchar

Silchar, Nov 22: A lawyer from Silchar has reached out to the Prime Minister’s Office (PMO) to clarify reports suggesting that the planned Silchar flyover may be shortened. He is questioning whether this alteration is being conducted through the appropriate channels.

In a letter dated November 20, Advocate Dharmananda Deb expressed his worries that the initially proposed 3.5-km flyover might now be divided into two segments measuring approximately 542 meters and 500 meters.

Deb inquired if the original 3.5-km project, which he claims received approval from the Assam Cabinet, remains the sanctioned plan.

He has requested information on whether any official body has sanctioned a modification to the project.

“Silchar does not seek assurances. Silchar seeks transparency, accountability, and the infrastructure development promised to its people,” Deb stated in his memorandum to the PMO.

This representation follows a review meeting held on November 20 to discuss potential changes to the flyover project.

Deb has also questioned the reported allocation of Rs 147 crore for land acquisition, asking for details on the land acquired thus far, compensation provided to landowners, and the implications for public funds if the original project is reduced.

He further inquired whether residents, landowners, and other stakeholders had the chance to voice their objections or opinions before any decisions were made.

Deb has requested information on the technical studies conducted for the original project, including soil and traffic assessments, as well as evaluations of alternative routes.

He emphasized that the matter extends beyond merely shortening the flyover; it also pertains to the principles of transparency and accountability.

Deb contended that a review meeting or public announcement cannot substitute for the necessary administrative approvals and technical processes required for altering a significant infrastructure project.

Copies of his representation have also been forwarded to Union Road Transport and Highways Minister Nitin Gadkari and Assam Cabinet Minister Krishnendu Paul for their awareness and action.