India's First High-Speed Rail Service Set to Launch in 2027: Key Updates from Railway Minister
High-Speed Rail Project Progress
New Delhi: On Friday, Railway Minister Ashwini Vaishnaw announced that India’s inaugural high-speed rail service is expected to begin operations in 2027, with the initial segment connecting Surat to Vapi.
He mentioned that the complete corridor to Mumbai will be opened in phases.
As of September, significant progress has been made, with 456 kilometers of pier work and 371 kilometers of viaduct construction already completed.
Noise barriers have been installed along a 299-kilometer stretch, and 9,300 overhead electrification masts have been erected across a 206-kilometer viaduct, according to Vaishnaw.
Furthermore, he noted that four mountain tunnels have been excavated, and 5 kilometers of the 21-kilometer tunnel in Maharashtra has been completed using advanced tunneling techniques.
Civil work has been finalized at eight stations, with architectural finishing currently in progress.
Construction is also ongoing at all three rolling stock depots located in Sabarmati, Surat, and Thane.
Regarding the undersea tunnel, Vaishnaw explained that the corridor includes a 21-kilometer tunnel, with 7 kilometers running beneath Thane Creek, marking India’s first undersea rail tunnel.
He revealed that two Tunnel Boring Machines (TBMs) were launched in July 2026 from Vikhroli and Sawli, which are among the largest ever used in India.
Each TBM features a cutterhead measuring 13.6 meters in diameter, equivalent to the height of a four-story building, and weighs over 3,000 tonnes, comparable to 500 Asian elephants. The machines are 96 meters long, roughly the length of five cricket pitches placed end to end.
Vaishnaw also highlighted the ongoing production of India’s first bullet trains, stating that ICF and BEML are working on the indigenous B28 trainset, designed for speeds of 280 km/h. The first body frame is complete and undergoing structural testing, with track trials anticipated by mid-2027. A faster model, the B35, designed for 350 km/h, is the next phase.
He emphasized that the fixed infrastructure is also being developed locally, with all major components of the high-speed electrification system being manufactured in India.
Addressing the nearly decade-long delay since the project's announcement in 2017, Vaishnaw explained that the project faced significant setbacks in Maharashtra due to pending state approvals and land acquisition, which took about two and a half years.
The COVID-19 pandemic further delayed progress by two additional years, with substantial construction commencing in earnest in 2021.
In response to critics questioning the bullet train's progress, he stated, 'Serious construction is just five years old. And look at what five years have built.'